Farrell Contracts were contracted by the EBOP contractor Reach Active to carryout the sub stn civil works for the 33Kv sub stn for the new Kingsbrook Housing development in Aylesbury.
Works comprised the following elements:
- Full building and civil works for the sub stn
- 200m dual tri foil ducting route link for new sub stn to the existing UKPN sub stn
Works commenced early Aug 2019 and we completed on time by early Dec 19 to meet the electrical installation programme.